Several paving projects are planned this summer in Jackson Township.
Generally, one lane at a time is paved to allow access to all homes after about a 30 minute delay for roller compaction and cooling of the hot asphalt. The other lane is open and maintained by flaggers to keep traffic moving through the construction zone.
The following streets are set to be repaved over the course of the summer and will be completed by Oct. 1:
- 38th Street, from Fulton to Whipple
- Amherst, from Fulton to Taggart
- Armistice, from Pontberry to Salerno
- Ballyshanndon, from Ponteberry to North Cds
- Bantry, from Armistice to West Cds
- Baycliff, from Island to North End
- Bayshore, from Baycliff to West End
- Bayside, from Baycliff to Shipslanding
- Beachland, from Baycliff to West End
- Beatty Amherst, to Shadyknoll to Pvmt.
- Bel-Air, from 38th to Zink
- Bel-Air, from Fulton to Bel-Air
- Butterbridge, from State Route 236 t0 special connector
- Community Parkway, from Fulton to Wales
- Fisher Park, from Lake O'Springs to West End
- Freedom, from Millwood to 6755 Freedom
- Harbor, from Armistice to Island
- Higbee, from Belden Village to South Curb End
- Holiday, from Higbee to Whipple
- Kerry, from Ponteberry to North Cds
- Maple, from Whipple to 524 feet east of Whipple
- Metro Circle, from Dressler to East End
- Michael Drive, from Bel-Air to 38th
- Millwood, from Promway to Freedom
- Munson, from Everhard to Dressler
- North Parking, from Community Pkwy N to highway entrance
- Pontebery, from Wales to East Cds
- Pontebery, from Wales to Armistice
- Promway, from Portage to North End
- Salerno, from East Cds to West Cds
- Shipslanding, from Harbor to Forestwood
- Sorrento, from Harbor to 6238 Sorrento
- Special Connector, from State Route 236 south to Butterbridge
- Traphagen, from 300 feet east of Amherst to 300 feet west of Amherst
- Willowcrest, from Everhard to Southeast Cds
- Zink, from Michael to Bel-Air
Several paving projects are planned this summer in Jackson Township.
Generally, one lane at a time is paved to allow access to all homes after about a 30 minute delay for roller compaction and cooling of the hot asphalt. The other lane is open and maintained by flaggers to keep traffic moving through the construction zone.
The following streets are set to be repaved over the course of the summer and will be completed by Oct. 1:
- 38th Street, from Fulton to Whipple
- Amherst, from Fulton to Taggart
- Armistice, from Pontberry to Salerno
- Ballyshanndon, from Ponteberry to North Cds
- Bantry, from Armistice to West Cds
- Baycliff, from Island to North End
- Bayshore, from Baycliff to West End
- Bayside, from Baycliff to Shipslanding
- Beachland, from Baycliff to West End
- Beatty Amherst, to Shadyknoll to Pvmt.
- Bel-Air, from 38th to Zink
- Bel-Air, from Fulton to Bel-Air
- Butterbridge, from State Route 236 t0 special connector
- Community Parkway, from Fulton to Wales
- Fisher Park, from Lake O'Springs to West End
- Freedom, from Millwood to 6755 Freedom
- Harbor, from Armistice to Island
- Higbee, from Belden Village to South Curb End
- Holiday, from Higbee to Whipple
- Kerry, from Ponteberry to North Cds
- Maple, from Whipple to 524 feet east of Whipple
- Metro Circle, from Dressler to East End
- Michael Drive, from Bel-Air to 38th
- Millwood, from Promway to Freedom
- Munson, from Everhard to Dressler
- North Parking, from Community Pkwy N to highway entrance
- Pontebery, from Wales to East Cds
- Pontebery, from Wales to Armistice
- Promway, from Portage to North End
- Salerno, from East Cds to West Cds
- Shipslanding, from Harbor to Forestwood
- Sorrento, from Harbor to 6238 Sorrento
- Special Connector, from State Route 236 south to Butterbridge
- Traphagen, from 300 feet east of Amherst to 300 feet west of Amherst
- Willowcrest, from Everhard to Southeast Cds
- Zink, from Michael to Bel-Air